Hi Leads,
Joseph and I have discussed the
possible issues that may occur during the execution of all the JCLs involved in
this ENVI Refresh.
1.
Number of JCLs – at least 200
objects that we will have to edit first before running
2.
Runtime of each job
3.
Possible errors – during past
experience in running JCLs that execute program(including the routine within
the executed program), there are instances that the program is not compiled in
the environment and also some BIND issues.
4.
Deadline (June 11) - irevokable deadline
With these, we want to request a
48-hour budget for each environment. Our plan is we will work on this from
Thursday (June 7) until Sunday( June 10) daily, 12 hours each day. This is to
maximize the time. Also, will there be a SUPPORT from SDC during the weekend
work?
Hiiiyang Hiya Naman Kami Sainyo Noh,
Itaremington